Home | Site Map   
      
      
 

- SAMPLE PROJECT PROPOSAL -

MODERN FRUIT PROCESSING & PACKAGING INDUSTRIES

        

1.

Name of the Project

:

MODERN FRUIT PROCESSING & PACKAGING INDUSTRIES
Installed Capacity: 500.00 Tonnes  per day

2.

Location within State/ Country

:

Bhalukpong, West Kameng District,
Arunachal Pradesh,India

3.

Nearest Rail, Road & Sea Connection

:

By Railway: from Bhalukpong :Rangapara, 20 Kms (Nearest Railway Station)
By Road from Bhalukpong : Balipara-18 Kms - Tezpur 28Km –Guwahati-175kms

4.

Estimated Capital Cost of the Project

:

Rs. 800.00Lacs (Approximately)

5.

Capital Equipment

:

Rs. 600.00Lacs (Approximately)

6.

Raw Materials

:

Kiwi, Apple, Pineapple, Orange etc.

7.

Environment Impact

:

If project cost is below Rs.1000.00 Lacs Environment Impact Assessment Consent from Ministry of Environment & Forest is not required.

8.

Foreign Exchange Cost Component

:

Not applicable

9.

Promotion Department

:

Department of Industries & Department of Agriculture & Horticulture

10.

Method of Selection of the Private Promoter

:

On the basis of policy framed by the State Govt. and Govt. of India.

11.

Policy framework applicable to the project

:

As per New Industrial Policies & Agriculture Policy  of the State Govt.

12.

Time-frame for selection of private sector sponsor/ developer

:

As convenient to Private sector sponsor.

13.

Government Incentives packages applicable to the project

:

All central Govt. incentives which comes under North-East Industrial Policy,1997, Tax Holidays, Price Preference, beside this special allotment of Power with low industrial power tariff rate among North-East State. And incentives provided by the Ministry of Food Processing Industries, GOI

14.

Expected level of Govt. participation

:

Co-ordination/monitoring in respect of implementation of the project. The Department assists in fulfilling the objectives of the project for the welfare of the state.

15.

Expected return on Investment

:

30% in the first five years. It may increase afterwards substantially.

16.

Recommended debt Equity Ratio

:

Bank Loan (60%) : Share Capital (40%):
Rs. 480.00 Lacs : 320.00 Lacs

17.

Expected Source of Financing

:

a) North-Eastern Development Financial Corporation Ltd.
b) Small Industrial Development Bank of India
c) Arunachal Pradesh Industrial Development  
   & Financial Cooperation Ltd.
d) Industrial Development Bank of India, etc

18.

Sovereign & Multilateral Guarantees

:

Private sector itself.

19.

Feasibility Report

:

--

 

 
 
 
Back
This website is designed and developed by National Informatics Centre
Arunachal Pradesh State Centre, Itanagar
Content is owned and maintained by Department of Industries, Govt. of Arunachal Pradesh
Best viewed in IE 6.0 at 1024 * 768 pixel resolution